Where I live, a local high way was ripped and paved the same day. They had a caravan of equipment 3 or 400 yards long. The leading machines ripped the old asphalt, the next cleaned it up, then the pavers laid the new asphalt followed by the rollers. They did one lane at a time. They finished several miles in a single day.